End User: Arc Resources Ltd.

Project: 138 kV Parkland Substation

Location: Dawson Creek, British Columbia

Start Up: 2018

Scope: Design & Manufacture.

Project Description:

  • The 25KV Metal Clad Arc Resistant Switchgear Electrical House c/w automatic transfer switch and 75KVA distribution transformer. 
  • Relay Protection Panels, BC Hydro Communication Rack and fire control panel
  • An enclosed battery bank and 2 x 50A 125Vdc chargers
138 kV Parkland Substation

Project Gallery