End User: SHELL – Albian Sands Energy Inc.
Project: Muskeg River Mine – Ore Prep Facility
Location: Fort McMurray, Alberta
Start Up: 2001
Scope: Design and supply the conveyor drive system for the surge feed conveyor, and breaker feed conveyors, site services for construction and commissioning.
Project Description:
- 1 surge feed conveyor, and 3 breaker feed conveyors, 14,000 tph
- Total installed power over 12MW